Short answer: High risk construction work (HRCW) is construction work on a list in section 291 of the Work Health and Safety Regulation 2011, such as work with a risk of falling more than 2 metres, work near energised electrical services or work where powered mobile plant is moving. Before any of it starts, the business doing the work must prepare a safe work method statement (SWMS).

What is high risk construction work?

It is a legal term, not a general description of dangerous jobs. Construction work is high risk construction work only if it matches one of the types listed in the regulation.

Queensland adopted the national model work health and safety laws, so the list matches the one Safe Work Australia publishes. It has 18 types of work.

The full list of high risk construction work

Construction work is high risk construction work if it:

  1. Involves a risk of a person falling more than 2 metres.
  2. Is carried out on a telecommunication tower.
  3. Involves demolition of an element of a structure that is load-bearing or otherwise related to the physical integrity of the structure.
  4. Involves, or is likely to involve, the disturbance of asbestos.
  5. Involves structural alterations or repairs that require temporary support to prevent collapse.
  6. Is carried out in or near a confined space.
  7. Is carried out in or near a shaft or trench with an excavated depth greater than 1.5 metres, or a tunnel.
  8. Involves the use of explosives.
  9. Is carried out on or near pressurised gas distribution mains or piping.
  10. Is carried out on or near chemical, fuel or refrigerant lines.
  11. Is carried out on or near energised electrical installations or services.
  12. Is carried out in an area that may have a contaminated or flammable atmosphere.
  13. Involves tilt-up or precast concrete.
  14. Is carried out on, in or adjacent to a road, railway, shipping lane or other traffic corridor that is in use by traffic other than pedestrians.
  15. Is carried out in an area at a workplace in which there is any movement of powered mobile plant.
  16. Is carried out in an area in which there are artificial extremes of temperature.
  17. Is carried out in or near water or other liquid that involves a risk of drowning.
  18. Involves diving work.

When is a SWMS required?

Before high risk construction work starts, the business carrying it out must prepare a SWMS, or make sure one is prepared. WorkSafe Queensland points to section 299 of the regulation for this duty.

  • It covers the high risk work, not the whole job. A cleaning SWMS covers the tasks that make it high risk, like working at height.
  • Each business prepares its own. WorkSafe Queensland's example: one contractor working above 2 metres and another running a crane each need a SWMS for their own work.
  • The principal contractor asks for it. On a construction project, the principal contractor must take reasonable steps to get a copy of the SWMS before the high risk work starts.
  • The work must follow it. If the work cannot be done the way the SWMS says, stop, review the SWMS and fix it before carrying on.

The 2 metre rule in Queensland

Construction work with a risk of a person falling more than 2 metres is high risk construction work, so it needs a SWMS. WorkSafe Queensland states this for both housing and other construction.

Do not mix this up with Queensland's separate fall-control thresholds. Specific fall prevention measures apply at 3 metres for housing construction and 2 metres for other construction, as WorkSafe Queensland's work at heights page sets out.

High risk construction work examples for cleaners

Cleaning on a building site is construction work when it is part of the project, such as a builders clean before handover. These are common cleaning situations that can fall into a listed type:

Cleaning situationType of high risk construction work it can fall into
Cleaning high windows or surfaces from a scaffold, EWP or near an open edge, with a fall risk over 2 mRisk of falling more than 2 metres
A builders clean while forklifts, scissor lifts or other powered mobile plant are movingMovement of powered mobile plant
Cleaning in plant rooms or near live switchboards and servicesEnergised electrical installations or services
Washing down beside a road that is open to trafficTraffic corridor in use by traffic other than pedestrians
Cleaning inside tanks, pits or similar enclosed spacesConfined space, if the space meets the definition
Cleaning around an open pool or water feature on siteWater or other liquid with a risk of drowning
Clean-up during refurbishment of an older building where asbestos may be disturbedDisturbance of asbestos

Common mistakes with high risk construction work

  • Listing things that are not on the list. Using chemicals or an elevated work platform is not a category on its own. EWP work is usually high risk because of the fall risk, and chemical work only if it fits a listed type.
  • One generic SWMS for everything. A SWMS has to match the work and the site. A template is a starting point that you adapt.
  • Writing it and filing it. WorkSafe Queensland has warned that a SWMS is much more than a piece of paper you fill in and then file. The work has to follow it.
  • Forgetting the people doing the work. Talk the SWMS through with your workers so they know the controls.

Do you need a SWMS for work that is not high risk?

The law only requires a SWMS for high risk construction work. Other tasks still need their risks managed, and many principal contractors ask every trade for a SWMS or a job safety analysis anyway.

For the difference between a SWMS and a JSA, read our plain-English guide to SWMS for cleaning contractors. Cleaners on site also need a White Card.

Need a starting point? Our SWMS templates are written for cleaning work and edit in Word. Adapt each one to your site and workers before use.

Frequently asked questions

Is cleaning high risk construction work?

Not on its own. Cleaning on a construction site becomes high risk construction work when it falls into one of the listed types, for example cleaning with a risk of falling more than 2 metres, or working where powered mobile plant is moving.

Is working from a ladder high risk construction work?

Only if it is construction work and there is a risk of a person falling more than 2 metres. Low ladder work below that height is not high risk construction work on fall risk alone, but it still has to be managed safely.

Is using chemicals high risk construction work?

Not as a category on its own. Chemical work is high risk construction work if it falls into a listed type, such as work in an area that may have a contaminated or flammable atmosphere.

Who has to prepare the SWMS?

The business carrying out the high risk construction work. If two contractors do different high risk tasks, each prepares a SWMS for its own work. On a construction project, the principal contractor must take reasonable steps to get a copy before the work starts.

Do I need a SWMS for work that is not on the list?

The law does not require a SWMS for work outside the list, but the risks still have to be managed. Many builders ask for a SWMS or a job safety analysis for every trade anyway.